Even though delays have prevented completion of the 2012 crack seal and asphalt overlay program, the city council voted to renew those contracts for 2013.

The St. Charles City Council voted Tuesday night to renew contracts for the 2013 asphalt overlay and crack seal programs.

A city memo noted the 2012 asphalt overlay program was 73 percent complete as of March 25 and the 2012 crack seal program was at 74 percent complete and that both projects were on hold due to weather conditions.

The memo noted the city was satisfied with the companies' production rates and quality of work and that renewing the contracts would allow for repairs to continue without further interruption.

Find out what's happening in St. Charleswith free, real-time updates from Patch.

The contract with Sweetens Concrete Services was renewed with a three percent price increase, with the 2013 project not to exceed $100,000 total cost.

The contract with Ford Asphalt Company was renewed with no price increase except for concrete, which will result in an average .15 percent total cost increase. The entire 2013 asphalt overlay project cost will not exceed $922,500.

Find out what's happening in St. Charleswith free, real-time updates from Patch.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here

More from St. Charles